@@ -0,0 +1,98 @@
|
||||
curl release procedure - how to do a release
|
||||
============================================
|
||||
|
||||
in the source code repo
|
||||
-----------------------
|
||||
|
||||
- edit `RELEASE-NOTES` to be accurate
|
||||
|
||||
- update `docs/THANKS`
|
||||
|
||||
- make sure all relevant changes are committed on the master branch
|
||||
|
||||
- tag the git repo in this style: `git tag -a curl-7_34_0`. -a annotates the
|
||||
tag and we use underscores instead of dots in the version number. Make sure
|
||||
the tag is GPG signed (using -s).
|
||||
|
||||
- run "./maketgz 7.34.0" to build the release tarballs. It is important that
|
||||
you run this on a machine with the correct set of autotools etc installed
|
||||
as this is what then will be shipped and used by most users on \*nix like
|
||||
systems.
|
||||
|
||||
- push the git commits and the new tag
|
||||
|
||||
- gpg sign the 4 tarballs as maketgz suggests
|
||||
|
||||
- upload the 8 resulting files to the primary download directory
|
||||
|
||||
in the curl-www repo
|
||||
--------------------
|
||||
|
||||
- edit `Makefile` (version number and date),
|
||||
|
||||
- edit `_newslog.html` (announce the new release) and
|
||||
|
||||
- edit `_changes.html` (insert changes+bugfixes from RELEASE-NOTES)
|
||||
|
||||
- commit all local changes
|
||||
|
||||
- tag the repo with the same name as used for the source repo.
|
||||
|
||||
- make sure all relevant changes are committed and pushed on the master branch
|
||||
|
||||
(the web site then updates its contents automatically)
|
||||
|
||||
on github
|
||||
---------
|
||||
|
||||
- edit the newly made release tag so that it is listed as the latest release
|
||||
|
||||
inform
|
||||
------
|
||||
|
||||
- send an email to curl-users, curl-announce and curl-library. Insert the
|
||||
RELEASE-NOTES into the mail.
|
||||
|
||||
celebrate
|
||||
---------
|
||||
|
||||
- suitable beverage intake is encouraged for the festivities
|
||||
|
||||
curl release scheduling
|
||||
=======================
|
||||
|
||||
Basics
|
||||
------
|
||||
|
||||
We do releases every 8 weeks on Wednesdays. If critical problems arise, we can
|
||||
insert releases outside of the schedule or we can move the release date - but
|
||||
this is very rare.
|
||||
|
||||
Each 8 week release cycle is split in two 4-week periods.
|
||||
|
||||
- During the first 4 weeks after a release, we allow new features and changes
|
||||
to curl and libcurl. If we accept any such changes, we bump the minor number
|
||||
used for the next release.
|
||||
|
||||
- During the second 4-week period we do not merge any features or changes, we
|
||||
then only focus on fixing bugs and polishing things to make a solid coming
|
||||
release.
|
||||
|
||||
Coming dates
|
||||
------------
|
||||
|
||||
Based on the description above, here are some planned release dates (at the
|
||||
time of this writing):
|
||||
|
||||
- May 22, 2019
|
||||
- July 17, 2019
|
||||
- September 11, 2019
|
||||
- November 6, 2019
|
||||
- January 8, 2020 (moved)
|
||||
- February 27, 2020
|
||||
- April 22, 2020
|
||||
- June 17, 2020
|
||||
|
||||
The above (and more) curl-related dates are published in
|
||||
[iCalendar format](https://calendar.google.com/calendar/ical/c9u5d64odop9js55oltfarjk6g%40group.calendar.google.com/public/basic.ics)
|
||||